Pump or main station

Start-up of new Installation

Start-up of Pump or Main station

  • Set air pressure to approx. 5 bar (Main station only)

  • Set function selector in Rinse mode (Main station only)

  • Slowly open inlet ball valve to fill pipes and pump with water

  • Open outlet to external and internal satellites to flush pipe

  • Check that water supply has sufficient volume and pressure of min. 1,5 bar

  • Check that air has sufficient volume, quality and pressure

  • Set chemical dosing

  • Check all functions (Rinse, foam and disinfection)

  • Clean filter on pump inlet after pipes have been flushed

  • Flush pipeline again through the internal satellite to take out eventual air